Timetable set out for Dartford Crossing toll booth removal

PUBLISHED: 12:31 13 November 2014 | UPDATED: 12:31 13 November 2014

Dartford crossing

Dartford crossing

Archant

Under Dart Charge drivers will no longer stop at a barrier to pay the charge

With the launch of Dart Charge set for November 30, more details have been announced today about how the Dartford Crossing payment booths will be removed.

Work to remove the booths and improve the road layout on approach to the crossing will begin on November 28 - the same weekend the new payment arrangements go live.

Highways Agency project director Nigel Gray said: “The payment booths have been part of the Dartford landscape since 1963 but they contribute to congestion and cause delays. That’s why they are being removed and we are introducing a new payment system called Dart Charge.

“From November 30, drivers will no longer pay at the booths. Instead they will pay in advance or by midnight the day after crossing, helping to speed up journeys.”

Under Dart Charge, drivers will no longer stop at a barrier to pay the charge.

Instead, they will pay online, by phone, by post or in one of thousands of payzone retail outlets.

Last week, the Highways Agency announced a new advertising campaign, part of a £1.1 million information campaign to help people prepare for the changes.

Dart Charge will come into effect at 6am on November 30, and the last cash payment will be taken at the Crossing around 10pm on November 29.

The new payment arrangements will signal the start of major work to improve the road layout at the Crossing with 27 lanes of traffic reduced to 4 in each direction and a new safety system of traffic signals and barriers on the approach to the tunnels northbound, which will prevent over-height vehicles from entering the tunnels, hold traffic in case of an incident or congestion in the tunnel, and allow the safe release of vehicles under escort (eg hazardous loads).

The roadworks will continue until spring 2015 when drivers will feel the full benefit of the changes through quicker journey times. Until then drivers can expect some delays but all work is being planned to minimise disruption. During construction temporary speed limits and road layouts will be in use so drivers should follow instructions on road signs.

Connect Plus is the organisation which operates the M25. Connect Plus Services is facilitating the delivery of the physical changes at the Crossing.

Erwan Huerre, Connect Plus Services transition manager said: “Initially, we’ll work to demolish the southbound booths and drivers should see the benefits travelling over the QEII Bridge after the first weekend of demolition. On the northbound side, the works will take longer to complete because we need to construct a new tunnel safety system.

“During this time, road users will still need to travel through the existing barriers, but they won’t be able to stop and pay here anymore. The reason we need to keep the barriers at this stage is to stop over-sized or non-compliant vehicles from using the tunnel.”

To find out more about Dart Charge, or to register for updates please visit www.gov.uk/highways/dartford

0 comments

Welcome , please leave your message below.

Optional - JPG files only
Optional - MP3 files only
Optional - 3GP, AVI, MOV, MPG or WMV files
Comments

Please log in to leave a comment and share your views with other Bexley Times visitors.

We enable people to post comments with the aim of encouraging open debate.

Only people who register and sign up to our terms and conditions can post comments. These terms and conditions explain our house rules and legal guidelines.

Comments are not edited by Bexley Times staff prior to publication but may be automatically filtered.

If you have a complaint about a comment please contact us by clicking on the Report This Comment button next to the comment.

Not a member yet?

Register to create your own unique Bexley Times account for free.

Signing up is free, quick and easy and offers you the chance to add comments, personalise the site with local information picked just for you, and more.

Sign up now

Latest Bexley news

Wednesday, December 12, 2018

A large development in Erith has taken home a top award for regeneration.

Tuesday, December 11, 2018

Since Bexley Council launched its anti-litter campaign earlier this year, 1,000 Bexley residents have now made the commitment to pick up at least one piece of plastic litter a week.

Monday, December 10, 2018

Our reporter Liam Coleman met with the big man before a hectic few weeks.

Monday, December 10, 2018

Crossrail, London’s new east to west railway service, may be delayed even further and could require a £2billion funding boost, Transport for London (TfL) has confirmed.

Monday, December 10, 2018

A faulty filtation system in a fish tank is believed to have caused a fire at a care home in Thamesmead on Sunday (December 9).

Friday, December 7, 2018

Rail travellers are now benefiting from recently completed work to improve access to Erith Station and to enhance the forecourt and station building.

A Bexley man who was suspected in the racist murder of Stephen Lawrence has admitted being a kingpin in a £4 million drugs plot.

Thursday, December 6, 2018

A burglar who stole three cars from homes in Dartford and Bexley has been sentenced to four years imprisonment.

Most read news

Digital Edition

Image
Read the Bexley Times e-edition today
E-edition

Newsletter Sign Up

Bexley Times twice-weekly newsletter
Sign up to receive our regular email newsletter

Our Privacy Policy

Show Job Lists

Family Notices 24